The Chief Commissioner of Railway Safety (CCRS), Janak Kumar Garg has completed the statutory inspection of the newly laid double line section between Barpeta Road & Pathsala stations on 2nd & 3rd June, 2024. The primary objective of this inspection was to ensure safety, security and operational efficiency of newly created railway infrastructure in this section.

This newly laid second line will be helpful for carrying more freights and passenger traffic through the New Bongaigaon – Agthori via Rangiya route and crossing time of trains will get reduced significantly.

Work of the Barpeta Road & Pathsala section has been done as part of the New Bongaigaon – Agthori via Rangiya 142.97 km long doubling project. The project includes 75 major bridges, 38 minor bridges and construction of 19 new station buildings.

The stretch between Barpeta Road to Pathsala is of 21.40 km. The section includes construction of 01 minor and 16 major bridges. There are 05 Level Crossings consisting 02 Special Class manned (Traffic), 01 Special Class & 02 “A” Class manned (Engg.) level crossings in the section. The second line was commissioned along with electrification.

The Chief Commissioner of Railway Safety (CCRS) inspected the railway bridges, track fittings, P-way assets, electronic inter-locking, relay rooms, cabin and level crossings in the section.

Adding to existing passenger amenities, 3-meter-wide new Foot Over Bridges have been commissioned at Sarupeta, Guagacha and Barpeta Road stations with 2 Bays & 10 Bays New Passenger Platform Sheds at Sarupeta and Barpeta Road respectively. One Ladies/Gents toilet each at Guagacha and Barpeta Road stations & 03 ladies/04 gents’ toilets at Sarupeta railway station were also facilitated.

Additionally, 02 new station buildings were also constructed at Sarupeta & Barpeta Road stations along with proper water supply for passengers at both the stations. Heights of the platforms were increased for ease of boarding and de-boarding of passengers from trains.

Out of the total 142.97 km of the New Bongaigaon – Agthori via Rangiya doubling project, 91.21 km has already been commissioned. Earlier 17.53 km section between New Bongaigaon to Bijni, 26.91 km section between Pathsala to Nalbari, 18.99 km section between Bijni to Sorbhog, 7.48 km section between Changsari to Agthori and 10.15 km Baihata to Changsari was commissioned on August 30,2022, 24th May, 13th June, 26th December, 2023 and 20th March, 2024 respectively. Also 21.40 km between Barpeta Road and Pathsala is commissioned today. On completion of this entire section, the regional train connectivity will get a significant boost.